How to scientifically select a concrete mixing plant? 7 key factors + cost – benefit analysis

Many construction bosses have fallen into such pitfalls when choosing a concrete mixing plant. They may spend 2 million yuan on equipment, yet the actual output is merely 60% of the claimed output. Or, in an attempt to save money, they opt for a smaller model, only to end up paying more in compensation due to project delays… In fact, choosing a mixing plant is akin to assembling a computer. It’s not about getting the most expensive option; rather, the key lies in “custom – tailoring according to requirements”. This article will show you, in the simplest way possible, how to identify the optimal solution in three steps.

Step 1 :Determine the requirements-First, clarify these four questions

1.How much concrete needs to be poured every day?

Customer pain points: Worry about over-purchasing(buying a larger-capacity one resulting in waste)or under-purchasing(buying a smaller-capacity one being insufficient)

Solution:

Simple formula:

Daily production requirement = Maximum single – pour volume × Maximum number of pours per day × 1.2 (safety factor)

Case:

“For example, a developer in a county wants to build 6 18 – storey residential buildings. The slab pouring of each building requires 300m³ of concrete and is completed in 3 times. Then:

Daily requirement = 300m³ × 3 times × 1.2 = 1080m³/day → An HZS120 – type mixing plant (with a theoretical output of 120m³/h) needs to be selected.”

2. What grade of concrete is needed?

Engineering typesCommon gradesConfiguration Requirements for the Mixing StationCost difference
Rural roadsC25-C30Self – falling mixer, diesel – powered$43,000-$72,000
High-rise buildingsC40-C50Forced – action mixer, computerized weighing system$115,000-$170,000
Hydropower station damsC60+Double – horizontal – shaft mixer, equipped with a chiller unit$215,000+

If you’re mainly building rural roads but buy high – end equipment for C50 concrete, it’s like using a Rolls – Royce to transport bricks — the performance is excessive, and you’ll also have to spend on maintenance!

Step 2 :Interpretation of Key Equipment Parameters

1. Deciphering the Model Naming Rules

  • HZS120: H stands for concrete, Z represents station – type, S means double – horizontal – shaft, and 120 indicates a theoretical output of 120m³/h.
  • Key point: The actual output is usually only 70 – 80% of the nominal output (for example, the actual output of HZS120 is approximately 85 – 100m³ per hour).

2. Three Core Parameters You Must Know

 

ParametersCommon MisconceptionsPit – Avoidance Guide
Mixing main engine capacity“3m³ can hold more than 2m³”A larger capacity doesn’t necessarily mean higher efficiency. It needs to be matched with the aggregate particle size (for capacities over 3m³, there are requirements for the size of the stones).
Discharging heightNeglecting the height of the tanker, resulting in splashingThe standard discharging height is 6 – 8 meters. For tunnel projects, a customized height – increased type is required.
Power configurationOnly looking at the power of the main engine while ignoring the total energy consumptionIn northern regions, a 15% power margin should be reserved to cope with low – temperature startup.

Step 3 : Cost analysis

1. Initial investment list

ProjectHZS60(small and medium-sized)HZS120(medium-sized)
Equipment price$64,000-$93,000$114,000-$171,000
Foundation construction$7,100-$11,400$14,000-$21,000
Installation and commissioning$4,300-$7,100$8,500-$14,200
Total$76,000-$111,000$137,000-$20,700

2.Hidden Cost Warnings

  • Difference in electricity costs:

           Forced – action mixers consume 15 – 25 more kilowatt – hours of electricity per hour compared to self – falling mixers.

  • Cost of vulnerable parts:
    “The mixing blades need to be replaced at least once a year. The unit price of blades for double – horizontal – shaft models is 40% higher than that of single – horizontal – shaft models.”

Related Posts